Escondido - New Multi-Purpose and Administration Building - Progress week of 3/11
Escondido - New Multi-Purpose and Administration Building - Progress week of 3/11
EL Building:
- Punchlist items are being recorded and addressed across the entire new Enrichment lab area, no noise impacts expected.
- Exterior painting is ongoing this week into next week, light compressor noise when spraying likely.
- Irrigation trenching is almost complete and soils testing will begin next week prior to landscape installation.
- Commissioning 90% complete
MPR/Admin Building:
- Canopy area joist work is nearing completion, and sheathing is ongoing. Expect frequent nail gun noise and minor compressor noise throughout the day.
- Fire sprinkler main and branch line nearing completion in the MPR space.
- Roof drains have been installed.
- Ongoing blocking throughout the space, will involve hand tool and saw use throughout the day.