Escondido - New Multi-Purpose and Administration Building - Progress week of 3/18
Escondido - New Multi-Purpose and Administration Building - Progress week of 3/18
EL Building:
- Irrigation work is finalizing their connections for the drip system.
- Landscaping soil tilling continues throughout the courtyard and back of building areas in preparation for planting. Light excavator use to be expected.
- Second coat of paint on the exterior is ongoing and nearing completion.
MPR/Admin Building:
- Liquid waterproofing at the roof level has been completed.
- Interior wall framing is 95% complete.
- Blocking is ongoing throughout the project and exterior sheathing will be completed this week.