Escondido - New Multi-Purpose and Administration Building - Progress week of 3/25

Escondido - New Multi-Purpose and Administration Building - Progress week of 3/25

EL Building:

  • Landscaping work will be ongoing throughout the week, will be mostly hand tool use without noise impacts.
  • Grade- all use to relocate boulders in and around the EL building will take place during the week, expect idling and beeping for several hours likely mid-week.
  • Final commissioning to take place on Wednesday.
  • Possible fire alarm testing on campus during the afternoon of Wednesday 3/27.

MPR/Admin Building:

  • Blocking and backing work continues, expect hand tool, saw, nail gun and scissor lift use throughout the week.
  • Electrical and Plumbing rough in continues throughout the week, no noise impacts anticipated.
  • Fire Sprinkler installation will complete the main phase of installation by Tuesday this week.
  • Final trenching and compaction work for seat walls as well as form and bracing work will take place over several days mid-week.  Small excavator and small dump use involving some idling and beeping.
  • Potential to begin some site work grading around the perimeter of the MPR building, would involve fairly consistent equipment use and beeping throughout the day beginning mid week.