Gunn High School New Gym

Project Overview

Gunn New Gymnasium is approximately 19,700 square feet and will be the new main gymnasium with bleacher capacity of approximately 1,900, a wrestling room, team rooms, a lobby, storage, offices, and restrooms. The new gym will be located to east of the Aquatics Center. The tennis courts and basketball courts will modified around the building, and the modernization of the existing Gym will include a new weight room and a new classroom.

Project Plans

Project Schedule

  • Architect Contract Approval – April 14, 2009
  • Conceptual Design Approval – September 22, 2009
  • Schematic Design Approval – January 26, 2010
  • Submit to DSA – August 4, 2010
  • Approval by DSA – May 27, 2011
  • Bid Opening – July 13, 2011
  • Award of Contract – July 20, 2011
  • Notice to Proceed – August 1, 2011
  • Substantial Completion – March 21, 2013*
  • Planned Occupancy – April 1 , 2013*