Paly's Media Arts Center will include a two-story classroom building and media production facility for the English Department. The structure features a two-story atrium with clerestory windows meant to accommodate large gatherings for multi-media presentations. Site improvements include an entry plaza, covered walkway, bike storage area and landscaping.

Project Plans

Project Schedule

  • Architect Contract Approval – April 14, 2009
  • Conceptual Design Approval – September 22, 2009
  • Schematic Design Approval – January 26, 2010
  • Submit to DSA – August 4, 2010
  • Approval by DSA – April 28, 2011
  • Bid Opening – June 30, 2011
  • Award of Contract – July 12, 2011
  • Notice to Proceed – August 4, 2011
  • Substantial Completion – September 20, 2013*
  • Planned Occupancy – January, 2014*