Palo Alto High School - Multi-use Field

Completed on February 1, 2011!

Project Overview

Paly's Multi-Use Field, a partially strong schools bond funded project, is a renovation of the softball and baseball fields, which will replace the fields with new turf, include new drainage systems, dugouts, fencing and batting cages.

Project Schedule

  • Architect Contract Approval – October 14, 2008
  • Conceptual Design Approval – January 13, 2009
  • Schematic Design Approval – March 17, 2009
  • Submit to DSA – March 19, 2009
  • Approval by DSA – September 30, 2009
  • Bid Opening – March 16, 2010
  • Award of Contract – April 7, 2010
  • Notice to Proceed – June 1, 2010
  • Substantial Completion – January 21, 2011
  • Planned Occupancy – February 1, 2011

Construction Updates

Multi-Use Field Project Progress Photos