Palo Alto High School New Classroom Building

Project Overview

Paly's New Classroom Building will include a two-story 27 classroom building for the Math and Social Sciences Departments. It features a teachers' office core flanked by two wings of classrooms connected by exterior covered walkways, multiple open stairways and an entry canopy. The building will incorporate new central plant service that will replace the adjacent existing central plant that will be demolished. Site improvements include an entry plaza, covered walkway, bike storage area and landscaping.

Project Plans

Project Schedule

  • Architect Contract Approval – April 14, 2009
  • Conceptual Design Approval – September 22, 2009
  • Schematic Design Approval – January 26, 2010
  • Submit to DSA – August 4, 2010
  • Approval by DSA – April 28, 2011
  • Bid Opening – June 30 , 2011
  • Award of Contract – July 12, 2011
  • Notice to Proceed – August 4, 2011
  • Substantial Completion – September 20, 2013*
  • Planned Occupancy – January, 2014*

 

Construction Updates