Project Overview

Paly's Athletic Stadium Improvements project scope of work includes a new concessions and restroom building with new entry tower. The building is 2,480 square feet, and it includes a concession area, a pantry, sports' teams storage area, a student store, and restrooms. The site improvements include resurfacing of the existing running track, new gateway entries and fencing, a new plaza, and a picnic area including paving and landscaping to the new bleachers. The bleachers include new aluminum bleachers for home and visitors sides for a total seating for 2,348, including a lift, accessible ramps and press box. Site improvements also include new long-jump, track and pits, new fencing, new paving and patching for ADA.

Project Plans

Project Schedule

  • Architect Contract Approval – February 9, 2009
  • Conceptual Design Approval – June 22, 2010
  • Schematic Design Approval – March 8, 2011
  • Submit to DSA – April 4, 2011
  • Approval by DSA – July 26 , 2011
  • Bid Opening – December 1, 2011
  • Award of Contract – December 13, 2011
  • Notice to Proceed – January 4, 2012
  • Completion - Concessions – September 10, 2012
  • Completion - Bleachers – March 31, 2013*