Jordan Middle School New Building Aerial View

Campus Profile

Greene Middle School
750 N. California Ave.
Built in: 1937, 1950, 1960, 1964, 1973, 1991, 2004

Greene Middle School is made up of 11 single story buildings on a 19 acre site on N. California Avenue. The original construction in 1937 included the Administration/Library wing, the Cafetorium, Gymnasium, Shop building, and 4 classroom wings. An expansion in 1950 added 3 classrooms and a shop classroom to existing buildings. The music building was built in 1960, and further additions and remodeling took place in 1964. The Cafetorium was rebuilt in 1973 after a fire in 1971. After closing in 1985, an extensive renovation of all classrooms was undertaken in 1991 prior to re-opening the school as a grade 6-8 middle school. During Building for Excellence, the school classroom spaces were again modernized with new finishes, lighting and heating systems. The Cafetorium and Gym were seismically upgraded and the lockers and showers were renovated.

Project Plans

Project Schedule

  • Architect Contract Approval – October 30, 2008
  • Conceptual Design Approval – September 8, 2009
  • Schematic Design Approval – April 27, 2010
  • Submit to DSA – December 21, 2010
  • Approval by DSA – October 5 , 2011
  • Bid Opening – December 8, 2011
  • Award of Contract – December 13, 2011
  • Notice to Proceed – December 27 , 2011
  • Substantial Completion – August 1, 2013*
  • Planned Occupancy – August 26, 2013*

* Anticipated Dates - Subject to Change